Interpreting successful results

In this example, Load Group 2 has the status Passed because all configured service level objectives (SLOs) were met.


  • User metrics (upper charts) show that HTTP response times remained well below the threshold of 1,000 ms throughout the run, with an average response time of 51 ms and a maximum of only 830 ms.
  • HTTP errors and automation errors both remained at 0%, confirming that no requests failed and the automation executed consistently.
  • The automation step duration chart indicates stable performance, with execution times showing some variation but without exceeding expected tolerances.
  • Infrastructure metrics (CPU and memory usage of executing robots) stayed within safe ranges, demonstrating that robot resources were not overloaded during the execution.

Because both application performance and infrastructure usage were healthy, this load group is marked Successful.